Home

I-84

  • I-84 Dual Bridge Replacement Project Continuing In Riverside

    Workers this week continued demolition/construction on the $6 million project to replace the two dual-lane Interstate 84 bridges that pass over Center Street in the Riverside section of Sandy Hook.

    The state Department of Transportation (DOT) recently created a “lane shift” on both the westbound and eastbound lanes of I-84 in the work area, allowing the second phase of the project to begin.

  • I-84 Traffic Shift Slated For Riverside Bridge Project

     The Connecticut Department of Transportation is announcing that traffic will be shifted on Interstate 84 to rehabilitate the bridges over Center Street in Newtown.  The shifts on Interstate 84 are scheduled for Tuesday night, June 10, 2014 for I-84 eastbound and Thursday, June 12 for I-84 westbound.

  • Evergreen Plantings Added To I-84 Bridge Replacement Project

    Evergreen tree plantings intended to improve aesthetics will now be included as part of an ongoing Interstate 84 dual-bridge replacement project in the Sandy Hook section.

    State Representative Mitch Bolinsky (R-106) in a statement on January 22 said that “noise mitigation” and a permanent safety barrier will be part of the project where I-84 crosses over Center Street in the Riverside section.

  • DOT Commissioner Hears Riverside Area Residents’ Complaints

    A group of residents from the Riverside Road area of Sandy Hook gathered around Connecticut Department of Transportation Commissioner James P. Redeker, State Representative Mitch Bolinsky, and First Selectman Pat Llodra on Friday, October 11.  Huddled in a circle near Center Street, residents voiced concerns about highway noise pollution and other related issues.

    Mrs Llodra said the meeting was a way to address the quality of life in the area.

  • Traffic Alert: I-84 To Be Closed Two Weekends At N.Y.-Conn. Border

    The New York State Department of Transportation is replacing two bridges carrying Interstate 84 over Dingle Ridge Road in Southeast, N.Y. The work is being accelerated to minimize traffic impacts, but will require the interstate to be closed in that area during two upcoming weekends.

    Traffic delays are anticipated. 

    The weekend of September 21-22, I-84 West will be closed at Exit 1 in Connecticut, and directed back onto I-84 at Exit 20 in Southeast.

  • Apparent Highway Suicide Resulted in Extended Travel Delays

     State police report that extended travel delays on Interstate 84 that occurred through the area on the afternoon of Wednesday, August 21, were caused by a police investigation into an apparent suicide that happened on westbound I-84, near Exit 5 in Danbury.

    State police said they received reports that a 52-year-old man had been spotted walking eastbound against the flow of westbound traffic on I-84 at about 12:45 pm, after which the man was struck and killed by a tractor-trailer truck.

  • DOT Advises That Bridge Construction Will Cause I-84 Traffic Delays

    The state Department of Transportation (DOT) advises that normal dual-lane traffic flowing on eastbound Interstate 84 between Exits 11 and 13 will be reduced to one lane of traffic on Tuesday, Wednesday, and Thursday this week from 9 am to 3 pm, each day, to allow certain construction to proceed on an I-84 bridge replacement project.

    The left lane on eastbound I-84 in that area will be closed during those periods.

  • Traffic-Lane Shifts Planned For I-84 Overpasses Above Center St.

    The state Department of Transportation (DOT) will be shifting the lanes of traffic flow on the two Interstate-84 bridges which cross above Center Street in the Riverside section of Sandy Hook.

    The construction work required to shift the location of traffic flow on the two 100-foot-long bridges is scheduled to start on Sunday, June 2, and continue to Friday, June 21. The parallel bridges lie about 90 feet apart from one another.

  • I-84 Bridge Reconstruction Plans Delayed

    State plans to shift the travel lanes on two Interstate-84 bridges, which cross above Center Street in the Riverside section of Sandy Hook, in preparation for a two-year dual bridge reconstruction project have been delayed for technical reasons, according to a state Department of Transportation (DOT) spokesman.

    DOT spokesman Kevin Nursick said this week that state officials are reviewing an issue concerning eastbound I-84’s existing bridge pavement geometry that must be resolved before a lane shift could be created on that bridge.