  • I-84 Bridge Work At Center Street About Half Done

    An ongoing $6 million state project to replace two Interstate-84 bridges, which cross above Center Street in the Riverside section of Sandy Hook, is about half complete, according to a state Department of Transportation (DOT) spokesman.

    Matthew Cleary, a transportation supervising engineer, said April 15 that construction work at the bridges resumed in early April following a cold, lengthy winter.

    “We just started back up for the [construction] season,” he said.