Date: Fri 18-Jul-1997
Date: Fri 18-Jul-1997
Publication: Bee
Author: DOTTIE
Quick Words:
construction-Hawley-NHS-ACMAT
Full Text:
School Building Projects: A Work Still In Progress
(with cuts)
BY DOROTHY EVANS
In some ways, a major construction project mirrors what happens in real life.
It takes surprisingly little time to tear something down, and a lot more time
to build something new in its place.
And no matter how carefully a project is planned and carried out, completion
schedules are always subject to change. In short, things happen.
These realities were brought home to Newtown Board of Education members at
their regular meeting July 8, as they heard reports on the progress of the
construction and renovation projects at Hawley School and at Newtown High
School.
It soon became clear that despite early delays in getting started, the $4
million Hawley addition and renovation project would probably come in on time
for school opening, Wednesday, September 3.
The $26 million high school project, much bigger in scope, will likely see
some delays in certain areas, and administrators are already looking at ways
to minimize the educational impact, where necessary.
Hawley Going Well
The Hawley project is now "in the final stages," said Mike Cifone,
representing the contractor, ACMAT.
The new addition is nearly completed except for dry wall, taping, installation
of tile, and lighting, he said.
Masonry and window replacement work at the core building is underway, and the
site work and parking lot paving work should be completed by the end of July,
he predicted.
"At the end of August we'll do a punch list," Mr Cifone said. A punch list is
a walk-through by the contractor and building inspector to note minor
last-minute items needing attention.
Hawley Principal Linda Siciliano was mainly concerned that staff be allowed to
enter the school as soon as possible before opening day, to enable them to get
their rooms ready.
Mr Cifone said that shouldn't be a problem, though Superintendent of Schools
John Reed voiced a concern that a thorough cleaning would be needed before
staff or students could reenter the building.
Apparently, a good deal of construction and demolition dust has entered the
interior environment and Dr Reed felt the contractor should pay to remove it,
since a drop cloth was not properly installed when a major wall was taken down
between the old building and the new addition.
"We need vacuums and wet mops," Dr Reed said.
Newtown Building and Site Commission Chairman Frank Krasnickas assured the
board that they would monitor the air inside the building before a certificate
of occupancy was issued.
High School Demolition Derby
At the high school, time tables for occupancy of certain spaces seem to be
slipping from earlier hoped-for estimates.
The fact is that by the end of the 1996-97 school year, only a little more
than half of the entire $26 million project had been completed - mainly in the
new addition at the north end.
Fully $9 million of interior work to the core building - involving a massive
amount of demolition to reconfigure the interior spaces - was still left to be
done. Of course, none of that work could begin while the students were still
in the building.
"All it is, is rubble," business manager John Torok said, describing the scene
in early July when he walked through the old school building and watched the
Bobcat tractors removing construction debris at a frantic rate.
When the demolition team had done its work, a cavernous space was opened up in
the second and main floors, where the walls and doors of the media center,
classrooms, main office, and cafeteria used to stand.
"This was an aggressive project to begin with. We knew that from the start,"
said George Graikoski, project manager for O & G Industries, which has been
overseeing both projects.
Disruption
Nearly a year since the high school project was begun late last August, a lot
has been accomplished, as any Newtown High student can attest who remembers
how the school looked at the end of last August.
Consider the shock of losing the entire north parking lot, the sight and noisy
presence of a seemingly non-stop parade of dump trucks hauling away the dirt
to excavate the construction hole for the new addition, and the view overhead
of exposed ceilings in the old building where new HVAC and infrastructure had
been installed in advance of construction.
Come opening day 1997, the high school scene will be quite different.
The entire project will still not be completed, according to Mr Graikoski, and
students, teachers, and administrators will, again, need to make adjustments.
"We have revised some of the completion dates," Mr Graikoski said, referring
to a flow chart he showed board members with time tables for various sections
of the project.
He mentioned contingency options and manpower issues that may become important
factors influencing completion dates.
In summary, this is what board members learned:
Most spaces in the new 74,000-square-foot addition will be available for use
on time, including classrooms, lab spaces, a lecture auditorium, and the
cafeteria and servery.
Spaces needing renovation in the core building will be ready as they are
completed, mostly beginning with the second floor and working down to the main
floor and basement levels.
Certain classrooms, such as art and music rehearsal spaces and the tech-ed
classroom, won't be available until November or even early December.
The culinary arts kitchen may be the last classroom to be completed, partly
because of the fire safety alarm system which can't be hooked up until all
other work on that level is done.
The locker room areas won't be done for a month after school opening, which
means no showers after gym in September.
Manpower An Issue
"We've got 170 workers on the site every day now, and we'd like to see 200,"
said Mr Graikoski, mentioning a manpower shortage in all the trades
experienced by the sub-contractors.
O & G Vice President Maurice Hoben said they were "calling in all their
chits," trying to get more workers on the job in order to move completion
dates forward as much as possible.
Newtown High Principal Bill Manfredonia had told O & G that completion of
second floor classrooms was a top priority, even if it meant that the media
center and main office areas were delayed.
Meanwhile, Mr Manfredonia said he expected that music classes could be held on
the auditorium stage, and art could take place in regular classrooms until the
new spaces were ready.
Band practice may have to happen outside.
Board members wanted to know why the contractors were just now reacting to the
manpower shortage, and why calls hadn't been made earlier to line up a
sufficient work force.
"You have to remember that the interior work on the core building didn't start
until June 17. We'd expect to see 20 men out there on a particular job and
only 12 would show up. Manpower is not a new problem," Mr Hoben said, adding
that one "problem" with the current healthy economy is full employment and no
workers waiting at home by the phone.