Iroquois To Explain Pipeline Expansion Plan
Iroquois To Explain Pipeline Expansion Plan
By Andrew Gorosko
The Iroquois Gas Transmission System has scheduled an informational session for Monday, April 23, to explain its proposal to build an additional section of pipeline in Sandy Hook as part of its plan to increase the volume of natural gas that it transports to Long Island, N.Y.
The meeting is scheduled for 6 pm at Reed Intermediate School Cafetorium, 3 Trades Lane. A general informational session will be held from 6 to 7 pm. A presentation of the pipeline expansion proposal and a question-and-answer period is slated for 7 to 8 pm.
Iroquois is seeking federal approval to construct a 1.6-mile-long section of buried, high-pressure natural gas pipeline near Lower Paugussett State Forest. The new pipeline would be installed parallel to an existing 11.3-mile-long Iroquois pipeline section that Iroquois constructed in Newtown between 1989 and 1991.
Many of the homes now standing in the area proposed for the new pipeline were constructed after the original Iroquois pipeline was installed.
The proposed 36-inch-diameter pipeline would be linked to the existing pipeline in a âloopingâ system designed to increase the volume of natural gas that the pipeline can transport.
The KeySpan Gas East Corporation natural gas distribution company wants to send additional natural gas to Long Island. The proposed Iroquois pipeline loop in Sandy Hook would be one of the components required for such increased gas distribution. The natural gas carried by the Iroquois pipeline is produced in western Canada.
The 1.6-mile-long pipeline section is proposed to extend along the companyâs right-of-way for its existing pipeline. The new pipeline would extend from the area near Canterbury Lane to the area near Stone Bridge Road.
About eight landowners abut Iroquoisâ proposed right-of-way. Iroquois likely would need to purchase land usage easements from some property owners, including the state, as part of the pipeline installation project.
It would probably take one to two months to construct the pipeline, which would be buried at least three feet below ground. Some blasting and tree removal would needed to install the pipeline. The proposed pipeline would run parallel to the existing pipeline, and be situated about 25 feet away from it.
In a statement, Iroquois explains that it would work with KeySpan to bring an additional 200 million cubic feet per day of natural gas into the New York City/Long Island market starting in November 2008.
 Iroquois is proposing to the Federal Energy Regulatory Commission (FERC) that it be allowed to construct additional natural gas facilities including pipeline looping sections in Sandy Hook, as well as in Boonville and Wright, N.Y. The firm also is proposing construction of a second gas compressor with cooling facilities in Brookfield, as well as a new gas compressor station in Milford.
Iroquois plans to submit a formal application to FERC late this summer.
Issues raised by the public at sessions such as the April 23 informational meeting would be addressed by Iroquois in its formal application to FERC. Those issues would be considered by FERC in its review of Iroquoisâ application.
Besides FERCâs review of the pipeline proposal, the project also is subject to review and approval by the US Army Corps of Engineers.
âWhen determining a route for a pipeline⦠many factors are taken into consideration, including safety, environmental impact, access, constructability, land use, economics, and public and landowner input,â according to Iroquois.
If Iroquois receives the required approvals for the pipeline project, construction could start in the spring/summer of 2008.
The project would include bringing workers and equipment to the site, preparing the right-of-way for construction, trenching, the installation of new pipe, and pipe testing. Site restoration work would follow the construction project.
âWith any of these projects, the devilâs in the details,â First Selectman Herb Rosenthal has said.
Issues posed by a pipeline installation project include how much disruption the project would cause to people living nearby, including activities such as truck traffic and blasting, he has said.