Date: Fri 20-Dec-1996
Date: Fri 20-Dec-1996
Publication: Bee
Author: STEVEB
Quick Words:
Booth-Library-schedule
Full Text:
Despite Setbacks Library Will Be Done On Time, Trustee Reports
B Y S TEVE B IGHAM
Library trustee Bill Lavery promised the people of Newtown Monday night that
the $4.1 million addition to the Cyrenius Booth Library would be done on time
and at or below budget.
Mr Lavery, responding to town officials' concerns that the project is lagging,
told the Board of Selectmen that despite the problems, the project is still
within its 14-month construction schedule.
Architect Bruce Tuthill of King and Tuthill Architects in Avon concurred,
saying the 22,000-square-foot structure is 68 percent complete and that though
it has hit its share of bumps, will be completed by June. Though two months
late, the architect said the projected completion date still falls within the
contract.
"Things have slipped, but we're still within the contract scope," Mr Tuthill
said. "The hard part is over. The building is up."
The architect said that despite the unforeseen problems, the project is
$278,745 under budget and $215,000 still remains in the contingency fund.
But as Legislative Council member Joe Mahoney pointed out, their positive
reports were in conflict to Frank Krasnickas' December 2 letter to the
architect, which suggested the possibility of terminating general contractor
James Galvin of Building Technologies Inc (BTI) and retaining a construction
manager.
"The Public Building & Site Commission is extremely concerned with the lack of
progress with the new addition," the letter stated.
It went on to say that commission members have questioned why the contractor
does not have sufficient planning or manpower on the job to enclose the
addition with the onset of winter.
Safety is also an issue, according to Mr Krasnickas' letter. Electrical cords
have been spotted submerged in water on the slabs, debris is still on all of
the floors, workmen framing and sheathing the roof rarely use safety
harnesses, and construction crews are working on floors covered with water and
ice.
Mr Krasnickas said that letter still stands, pointing out that materials, such
as sheet rock have been damaged.
Also, the addition was to have been enclosed December 1, but that has been
delayed.
"Things are going slow as far as we're concerned," Mr Krasnickas said. "The
contractor blames the hold up on the asbestos abatement, but that has nothing
to do with the outside addition."
The architect predicted the roof would be enclosed by the end of this week,
but the project's clerk-of-the-works Ed Callo said that would take some form
of divine intervention.
"I realize this is the Christmas season and miracles do happen, but I don't
see the roof being enclosed by the end of the week," he said.
In the meantime, interior contractors must wait to begin work inside, further
delaying the project.
The library project didn't get off to a good start. Construction was delayed
until March, 1996, which forced BTI to bring in "poor" sub-contractors who had
to be removed and a superintendent who quit. From there, asbestos was found
within the existing building, forcing it to be closed for abatement work.
The asbestos removal is about 90 percent complete, according to Mike Buckley
of PETCO.
Paving and landscaping were also delayed when fill was not brought in on time.
"It's not good management by the construction company. That's what it sounds
like to me," said Mr Mooney.
Upon questioning, Mr Tuthill said hiring a construction manager this far into
the project would not be practical.
Mr Mooney also took exception to the fact that if the library board wants
something done or changed it goes to the Public Building Committee (appointed
by selectmen), which usually acts without authorization from the Board of
Selectmen.
"The ultimate responsibility will end up right at this (selectmen's) table and
we're not giving any input to this," Mr Mooney said.
But as Mr Lavery pointed out, the library board has unique statutory power
over the library and has vowed to keep a close eye on the project.
"We have tight control because we are not going one cent beyond the
expenditures allowed by the town. The job will not go over budget," Mr Lavery
said. "There have been problems but we're within the time frame and we're
pushing."
The selectmen requested that Mr Krasnickas come to their next meeting for an
updated report on the project.
"We just want the job to get on track and get done in time," First Selectman
Bob Cascella said.
