Date: Fri 22-Nov-1996
Date: Fri 22-Nov-1996
Publication: Bee
Author: DOTTIE
Quick Words:
schools-construction-projects
Full Text:
with cuts: Ecstacy And Agony: High School And Hawley Progress Reports
B Y D OROTHY E VANS
There was good news and not so good news last week concerning the construction
timetable for the town's two biggest school building projects at Newtown High
and Hawley School.
The two projects, which were approved by voters in June 1996 and which will
cost a total of $29 million to complete, are both well underway with plenty of
construction activity evident on the sites - but there the similarity ends.
When educators at the November 12 Board of Education meeting heard an update
on both projects from the architect, site manager and town building chairman,
these reports drew mixed reactions ranging from optimism to concern and
consternation.
Progress At The High School
The $25 million Newtown High School addition and renovation project, which
includes construction of a three story 74,000 square-foot addition on the
school's north side, renovations to existing sections of the building, a new
roof over part of the school, HVAC updates, a new half-gymnasium behind the
school, and construction of 100 more parking places, is on schedule.
It might even be slightly ahead of schedule, the town's building commission
chairman told the board.
"It's moving right along," said Public Building and Site Commission Chairman
Frank Krasnickas.
Mr Krasnickas said that "in 20 years, this is the first time I've seen steel
go up and fit the first time."
Now that the structural steel is in place, workers are pouring cement for the
elevated slabs, or floors, Mr Krasnickas said. Plumbing and electrical work is
also underway in the addition, and the sub-contractors have finished
installing electrical service in the boiler room area.
"We've got a head start for summer work," Mr Krasnickas said.
The addition will house a kitchen, servery, and cafeteria on the lower level,
11 classrooms and a large group instruction room on the main level, and 17
classrooms, science labs and a computer lab on the upper level.
He concluded with an estimation that the high school project would be
completed in May 1997 as planned.
The interior renovations to the present high school building that were begun
over the summer but halted while school is in session, will be completed as
soon as school ends in June.
Catch-Up At Hawley
The prospect for finishing the $4 million Hawley School addition on time (by
the beginning of August 1997) is not so promising, according to Mr Krasnickas.
"They have installed a new pathway to the playground that has no access to the
construction area," he said, adding that school officials were relieved to
have that safety precaution in place.
But no steel has gone up.
"They're installing the storm drains around the building and working on the
footings and walls. They hope to have the steel by the end of the month," Mr
Krasnickas said.
If bad weather interferes, they'll encapsulate the building in plastic, he
explained. Moisture accumulation inside the building might then be a problem,
however.
The bricks can't be laid on the outside walls until spring, he added.
"I will say they're making an effort, though, because they've got a second
shift on the job," Mr Krasnickas noted, referring to efforts by the
contractor, ACMAT, Inc. of New Britain, to meet construction deadlines.
Rusty Malek, the architect with New Britain architectural firm Kaestle Boos
Associates, Inc., that submitted the designs for both the high school and
Hawley projects, spoke to the board of his frustration at the lagging Hawley
project schedule.
"It seems the beginning of a job usually tells you how it's going to end up,"
he said, referring to the fact that ground wasn't broken until late September,
nearly a month later than planned.
He then mentioned the many letters he has had to write, "sometimes three or
four a day" to the contractor, enumerating what he called "holes in the
schedule."
"The contractor [ACMAT] says we're two weeks behind. I would be smiling if it
was that little!" Mr Malek said.
Despite his stated concerns, Mr Malek said the contractor continued to insist
the job would be completed on time.
"It hasn't been easy... a struggle all the way," Mr Malek said.
The one redeeming factor, he said, was the fact that ACMAT had retained "good
sub-contractors all the way."
Maurice Hoben, vice president of O&G Industries, Inc., the company that was
hired by the board to manage both projects, was in a similarly pessimistic
mood about the Hawley project outcome.
"We're spending three quarters of our time at Hawley. This may be a photo
finish, I'm afraid," Mr Hoben said.
School officials had hoped to have the 22,000 square foot Hawley addition
completed by the beginning of August in time for school opening after Labor
Day. It will include an auditorium, a new library media center and several
classrooms.
Redistricting plans call for moving approximately 110 students from the Sandy
Hook School district to the expanded Hawley School beginning in September
1997.
