Date: Fri 06-Dec-1996
Date: Fri 06-Dec-1996
Publication: Bee
Author: ANDYG
Quick Words:
sewers-Whitten
Full Text:
Sewer Project Is About 80 Percent Complete
B Y A NDREW G OROSKO
The town's sanitary sewer construction project is about 80 percent complete,
according to John Whitten, senior field representative for Fuss and O'Neill,
Inc, the town's consulting engineer.
Work on the $34.3-million project is expected to conclude next fall.
Baltazar Contractors' workers were on Mt Pleasant Road this week doing some
preliminary construction work, Mr Whitten said. The workmen plan to return to
that area next spring to extend sewer lines from the intersection of Mt
Pleasant Road and Diamond Drive to the base of Mt Pleasant Road, near the
Newtown Volunteer Ambulance Corps garage.
During this week, sewer installers were placing pipe under East Street, a
short dead-end road that extends eastward from Main Street near Edmond Town
Hall. Traffic delays ensued on Main Street as police stopped motorists to let
heavy equipment cross the road.
Mr Whitten said that upcoming winter weather shouldn't pose any problems to
work crews who plan to use directional drilling to install sewer pipes along
the east side of Main Street, between East Street and Glover Avenue.
Directional drilling will be used to minimize the damage done to the many
large trees lining the thoroughfare.
Work on the sewage treatment plant at the end of Commerce Road is progressing
so well that it is actually ahead of schedule, Mr Whitten said. Workmen expect
to link the end of Commerce Road to the treatment plant site by January, he
added. The existing turnaround at the end of Commerce Road will be eliminated
and a new turnaround will be built farther to the east to provide access to
the plant.
Construction specifications are out to bid on four sewage pumping stations.
The stations will pump sewage uphill from low points on the periphery of the
sewer system.
West Street has received a final repaving after having been torn up for sewer
line installation. Wendover Road, The Boulevard and Budd Drive also have
received their final repavings, according to Mr Whitten, who serves as the
chief sewer inspector.
Still scheduled to receive their final new surfaces are the "Presidential"
streets, and also Juniper Road, Baldwin Road, Nettleton Avenue and Birch Rise
Drive.
Workmen started sewer construction in November 1994, and except for periods of
extreme weather during winter seasons, have continued digging the miles of
trenches for the sewage collector system which traverses the Borough, Taunton
Pond North, and Sandy Hook Center.
After the sewer system is complete, the town will set a time period during
which residential and non-residential customers will be required to connect
their wastewater drains to the system. The length of time that sewer users
will have to connect to the system hasn't yet been set by the Water Pollution
Control Authority (WPCA). The "out of pocket" costs that sewer users will bear
to connect to the system will vary depending on the complexity of their
particular sewer hookup.
After the new joint municipal-state sewage treatment plant is operating, the
sewage now treated by Fairfield Hills' existing treatment plant will be
diverted to the new plant. Sewage flows to the plant will then gradually
increase as an increasing number of municipal customers connect to the system.
When it is complete, the sewer system will include approximately 23 miles, or
about 121,000 feet of sewer mains and lateral sewer lines, Mr Whitten said.
That figure doesn't include the amount of sewer drainpipe which will extend
from buildings to the lateral lines.
Building a municipal sewer system was discussed for decades before voters
approved bonding for the project in 1992. The system is being built to rectify
longstanding groundwater pollution caused by failing septic systems.
