Date: Fri 30-Aug-1996
Date: Fri 30-Aug-1996
Publication: Bee
Author: KAAREN
Quick Words:
sewers-assessments
Full Text:
with chart: Officials Try To Nail Down Town Costs For Sewers
B Y K AAREN V ALENTA
With the date of the expected completion of Newtown's sewer system just one
year away, town officials want to know exactly what it is going to cost the
local taxpayer.
At their meeting last week, members of the Legislative Council said the Water
Pollution Control Authority needs to decide by the end of the year how much
the town will be assessed for municipal buildings which will be hooked to the
new sewer system. The council says it needs the figures to determine how much
tax revenue will have to be raised to pay the bill.
Earlier this year the WPCA set the residential assessment at $9,900, to be
paid back by property owners in the sewer district over 20 years at an
interest rate of two percent. These homeowners also will pay a one-time hookup
fee and an annual sewer usage charge. But the WPCA has yet to set the
assessment formulas for municipal and commercial/industrial sewer users.
When sewer construction began nearly two years ago, the council thought it
would only have to pay to hook town buildings to the sewer system plus the
annual user fee. So the council put aside $500,000 in the reserve account for
capital and non-recurring expenditures to pay for the hookups. Last winter the
council learned that town buildings also will be assessed.
Like homeowners, the town has access to loans which can be paid off over 20
years at an interest rate of 2 percent. But the money to make these payments
must be included in the 1997-98 budget because the bills will begin once the
sewer system goes on line in September 97.
Finance Director Benjamin Spragg said it has not yet been determined how the
repayment will be structured for the $18.5 million loan which the town will
receive from the state through the Clean Water Act. "One of two methods will
be used - level principal or level debt," he said. "In a level debt, the same
payments are made for 20 years. In a level principal, more is paid at first
and payments decrease over the 20 years."
"Whichever method is used by the town probably will be the same method used
for homeowners - it would be prudent to match the two methods," he said.
With a level debt repayment method, homeowners in the sewer district would pay
$601.08 a year for 20 years.
Council Member Joseph Borst said he has asked the Connecticut Conference of
Municipalities for information about how other towns handled municipal sewer
assessments and whether they even assessed the town-owned buildings.
Council Vice Chairman Melissa Pilchard said she is concerned not only about
municipal assessments but about the financial impact of the assessments on
businesses in Newtown.
"The first figures I heard a year ago (for commercial/industrial users) were
frightening," she said.
Peter Gross, project manager for Fuss & O'Neill, Inc, of Manchester, the
company which the town hired to supervise construction of the project, said
the anticipated completion is September 1997 "or a month or two before that."
"We are well ahead of schedule," he said.
Approximately 70 percent of the piping has been laid, the sewer plant is 30
percent complete and more than half of the money allocated for the project has
been spent, he said.
Eight of the nine contracts have been bid. Contract 3A, for directional
drilling along Main Street to avoid tree roots, was scheduled to be awarded
this week. The ninth contract, for pumping stations, will be bid within the
next few weeks.
The original engineer's opinion of the total sewer construction cost was $25.6
million. The bids came in at $22.7 million but some changes which were
required have pushed the total up to about $23.5 million. Last week voters at
a town meeting also approved using up to $600,000 to bring a sewer line to the
high school, if necessary, and $660,000 for a septic repair program for
property owners outside the sewer district. Altogether, the sewer project
costs now total about $31.75 million.
Voters several years ago approved a maximum of $34.3 million in bonding for
the sewer project. They also agreed to pay one-third of the capital cost of
the project through the general tax rate with the other two-thirds to be paid
by property owners within the sewer district.
Nearly 20 miles of pipe are being laid in the borough, Taunton and Sandy Hook
Center .
John Whitten, supervisor of the project, told the council that Currituck Road
has to be repaired because a water main broke over a weekend and it took 12
hours for the leak to be found and repaired. A new gas main also will be laid
on Queen Street before the final paving is done, he said.
Drainage work is being done on The Boulevard. Lateral lines will be installed
from the sewer mains to the houses, then a binder will be spread on the road
before winter.
Mr Whitten also explained why concrete sidewalks were being installed in front
of some of the offices along Church Hill Road and asphalt sidewalks in front
of others.
"We are required to put back exactly what was there," he said. "We asked the
DEP (State Department of Environment Protection) if we could use all concrete,
but the DEP said no because concrete is $27 a foot. Asphalt is $1 a foot."