Date: Fri 09-Aug-1996
Date: Fri 09-Aug-1996
Publication: Bee
Author: STEVEB
Quick Words:
projects-Krasnickas
Full Text:
Capital Projects Keep Building Committee Chairman Running
B Y S TEVE B IGHAM
Frank Krasnickas made his rounds this week, updating town boards and
commissions on the various capital projects going on in town.
The chairman of the Public Building and Site Committee has been especially
busy lately with additions and renovations underway at the Cyrenius Booth
Library, Newtown High School and Hawley Elementary School.
He has been putting in six to seven hours per day five days a week on the
projects as a volunteer.
"I'm busier than hell. It's like a full-time job," said Mr Krasnickas, who
says he's been chairman of the committee for more than 10 years.
He met with both the Board of Education Tuesday and the Legislative Council
Wednesday and fielded questions.
Mr Krasnickas reports the asbestos removal at the high school continues, and
though the work is a bit behind schedule, it was is to be completed late this
week. He said one of the problems came about after the contractor put down the
wrong floor sealer.
Also, the NHS parking lot's resurfacing is expected to be completed by August
19. Ceiling demolition and new footings for the NHS addition are also being
done, according to Mr Krasnickas.
In all, 13 contractors for the high school project have still not been signed,
though Mr Krasnickas said all have been committed. According to Mr Krasnickas,
a mechanical contractor has been doing work on site, even though the company
has yet to sign a contract.
Mr Krasnickas said a contract was signed with ACMAT, the company hired to
build the Hawley addition, on July 12.
In the meantime, workers are putting up a divider in the library, transforming
it into two classrooms, and a temporary septic system is being installed in
the front of the building.
At Hawley, a temporary access-way will be built to the playground behind the
school.
The two school projects, expected to cost in excess of $30 million, are mostly
under the control of the Board of Education and the Public Building Committee,
but council member Pierre Rochman believes the council needs to be better
informed about financial matters and not "left in the dark" as he claims it
has during past school projects. He questioned Mr Krasnickas as to where the
buck stops with the high school and Hawley projects.
"Who are we reporting our financial concerns to," he asked.
Member Joe Borst reminded the council that it is not responsibility of the
council to "micro-manage" large capital projects.
The council voted Wednesday to have Mr Krasnickas report quarterly on the
projects.
At the library, Mr Krasnickas said 80 percent of the steel has been erected
and the major demolition of the existing building will begin at the end of the
month and run through September 12. During that time, the library will be
closed.
The Building Committee chairman reported that duct work is currently being
installed in the old section of the library. Mr Krasnickas told the council
that he and the building inspector had agreed that the duct work so far should
be changed, prompting an angered outcry from First Selectman Robert Cascella,
who expressed frustration about quality of the work being done and materials
being used at the site.
In June, H&H Construction was replaced after some concrete forms it poured
were defective because supplementary plywood used was not properly reinforced.
That, plus other unspecified problems have plagued the project, prompting the
outburst from the frustrated first selectman.
"The library has been a problem for three consecutive months," he shouted.
"It's not the selectmen's fault. It's not the Legislative Council's fault.
It's not the Building Committee's fault. Who's fault is it?"
Through the harsh words came a bit of humor.
Mr Borst, who once served on the Building Committee, was under the impression
that when bills are paid for construction costs, signatures from both the
school board chairman and building committee chairman were required. Mr
Krasnickas said he's been the only one signing checks of late.
"I remember needing two signatures when I was on the Building Committee," Mr
Borst noted.
"They trust me. They must not have trusted you," Mr Krasnickas replied in
jest.
Wondering how he found time to do all that he does, council member Melissa
Pilchard thanked Mr Krasnickas for his dedication to the town of Newtown.
