Date: Fri 14-Jun-1996
Date: Fri 14-Jun-1996
Publication: Bee
Author: KAAREN
Quick Words:
Town-Hall-South-renovation
Full Text:
Selectmen Endorse Town Hall South Renovation
B Y K AAREN V ALENTA
The Board of Selectmen Monday night unanimously approved the expenditure of
$840,000 to renovate Town Hall South. The proposal will be presented to the
Legislative Council next week and also must be approved by voters at a town
meeting.
The selectmen recommended that the money to pay for the project come from the
town's Reserve Fund for Capital and Non-Recurring Expenditures, a fund which
currently has a balance of more than $2 million.
"This is a small investment to get what will look like a new police department
and town hall annex," said First Selectman Bob Cascella. "The building has
been in a state of disrepair for years, and no amount of maintenance now can
fix it. The people who worked in the flooded conditions in Town Hall South
this past winter went well beyond the call of duty.
"That corner will look nice - really sharp - when the work is done," he added.
Architect John Madzula told the selectmen that the building renovation cost is
estimated at $678,000. Another $30,000 will be needed for site development
which includes such expenses as landscaping, paving, curbing, striping the
parking lot and minor drainage work, most of which will be done with town
labor. About $10,000 will be needed to relocate the 911 air conditioning unit
and antennas on the building, which also houses the police department.
Mr Madzula said $105,000, or about 15 percent of the project cost, would be
set aside for contingencies, and $17,000 for architect/engineer fees.
"There are a lot of town officials in the building to provide supervision of
the project (the fees) hopefully will be a lot less," he said. "The cost is
based on an hourly rate spread over an estimated six-month construction
period."
Last year the council informally earmarked $250,000 of the reserve fund for
the project. An additional $575,000 of surplus funds were added to the reserve
fund as part of the 1996-97 budget with the Town Hall South project in mind
although money cannot be officially allocated until the money is withdrawn
from the reserve fund. According to the town charter, all expenditures of more
than $50,000 must go to a town meeting for a vote.
This spring much of the tile flooring and wallboard was removed from the
Planning & Zoning Office on the lower level of the building at the order of
the Occupational Safety and Health Administration (OSHA) because of repeated
damage caused by flooding. A major repair of the curtain drain around the
building is planned as part of the renovation project.
The proposed project also includes a new pitched roof to replace the existing
flat roof, new single-hung windows to replace the existing sliders, brick
siding on all four sides of the building, and enclosure of the parking ramp
area to create 5,000 square feet of additional space for future office
expansion. Carpeting repeatedly soaked by leaks in the lower level will be
replaced with tile flooring. New sheetrock will be installed in the damaged
areas, any damaged studs will be replaced and the electrical system will be
repaired. All work must comply with new state building codes.
When the project went out to bid last year, Clearheart Construction Company of
Bethel was the low bidder with a base bid of $758,000, well above the original
estimate of $500,000. With all eight of the alternate proposals included, the
total construction bid was $893,385. Efforts subsequently were made to reduce
the cost of the project.
Mr Madzula said an engineering consulting firm used by the town on other
projects was hired to do "value engineering," a process that identifies where
savings can be made without a detrimental effect on the project. He said the
engineers determined that less structural steel could be used to enclose the
parking ramp area. Other savings were realized by using a different window
manufacturer, he said.
"We've been working on this project for almost a year now," Mr Madzula said.
"Hopefully we're at a point where we're ready to go ahead."
During the construction, the built-up roof will be torn off but the metal
decking will remain and will be covered to prevent rain from leaking in.
"We've told the contractor that the police department must be kept in
operation 24 hours a day, seven days a week," Mr Madzula said.
He said the decision was made to include $105,000 for contingency because it
isn't known yet whether there may be contaminated soil that would have to be
disposed of as hazardous waste. Before the town bought the property in the
mid-1970s, the building served as a farm implement salesroom and repair
facility.
While waste oil could have been dumped outside the building decades ago,
ground water samples tested during the flooding of the building earlier this
year showed no traces of contamination, Mr Cascella said.
A committee which included Mr Cascella, Public Works Director Fred Hurley and
Legislative Council members Joe Borst and Win Ballard has been overseeing the
planning of the project.
The proposal is slated to be on the agenda of the Legislative Council meeting
which will be held at 8 pm on Wednesday, July 17, in the Middle School
library.
