Date: Fri 20-Dec-1996
Date: Fri 20-Dec-1996
Publication: Bee
Author: DOTTIE
Quick Words:
schools-projects-NHS-Hawley
Full Text:
School Building Update: It's All About Steel
B Y D OROTHY E VANS
Talking with Public Building and Site Commission Chairman Frank Krasnickas
about how things are going at the Newtown High and Hawley School construction
sites, a person can't help noticing that one particular word keeps cropping
up.
That word is steel.
The presence or absence of structural steel is significant in several ways.
To the casual observer, watching steel go up at a building or addition site is
visually satisfying. It seems that almost overnight a new space is framed,
with trees, clouds and sky showing through, where walls, floors and ceilings
will eventually obstruct the view.
When the steel framework is completed, the new structure becomes visible and
occupies a finite space.
But to a building chairman, a contractor or a school administrator, the sight
of steel framing means a great deal more.
Having followed the construction project from its earliest stage, they know
that important underground work has already been completed. Such as excavation
and removal of dirt, pouring of cement footings and foundations, drainage
work, ground level plumbing and electrical work.
According to Mr Krasnickas' perspective, when the steel goes up, "It's a good
start."
"You're not halfway done with the project yet, but it's a beginning."
Out Of The Ground
At Hawley
Early Monday morning, Mr Krasnickas was happy to report that the contractor
had finally delivered steel to the Hawley School addition site.
It had been a suspenseful two-week waiting period, he said, during which the
contractor, ACMAT, Inc., of New Britain, continued to express optimism about
imminent delivery of the steel, and the building inspector fretted about
delays.
Once it had arrived and the columns were raised, Mr Krasnickas said, work
could begin on pouring the cement floors, roofing, HVAC installation, plumbing
and electrical conduits, framing of windows and doors, wallboard, fixtures and
floor finishings.
"They've been unloading steel and putting up the columns," Mr Krasnickas said,
adding the column plates had been prepared in advance so no time would be
wasted.
A delivery of insulation for the new gymnasium ceiling in the present school
building was also made, he added.
Mr Krasnickas said that additional work on asbestos removal, piping and
electrical conduit had been done inside the current school building, "so
connections could eventually be made between with the addition."
Hawley School principal Linda Siciliano was less reserved in her enthusiasm.
"When the crane came in there was so much excitement," Mrs Siciliano said
Tuesday morning.
"The steel was going up so quickly, and they've been working a second shift
inside the school after the kids leave," she said.
"I feel confident we'll have school opening in September as planned," she
added.
The $4 million Hawley School addition and renovation project is scheduled for
completion in early August 1997. The addition is planned to house a library
media center and several classrooms.
Progress At
The High School
Mr Krasnickas said work was pretty much on schedule at the Newtown High
construction site, where a $25 million three-story addition is being built on
the north side of the school.
"They just completed pouring the concrete for the main level floor," he said.
The half-gymnasium at the back of the school, also part of the same project,
is on schedule, Mr Krasnickas added.
"All the steel is up on the main addition. In back, we've got the steel frame
up for the add-on gym. Things are looking good," he commented.
The main level floor, which appears to be at ground level to an outside
observer, is really the second story of the three-story addition.
The lower, or basement, level is underground and has been completely closed
in. Mr Krasnickas said "underground work" by the subcontractors is going on
there now. That level will house the kitchen servery, cafeteria and a future
expansion area.
The main level will contain classrooms, computer labs and areas for large
group instruction. The upper level will contain science labs and classrooms.
Although the addition roof is not on yet, its nearly flat profile can be
discerned by studying the outline of the steel supports that frame it. A
slight pitch has been built in, Mr Krasnickas said, to facilitate drainage.
When it is completed, the addition will add 74,000 square feet to the high
school, connecting to the existing building at the main and upper levels.
Weather Hasn't Helped
Mr Krasnickas expressed frustration about one factor that is affecting both
projects and over which he has absolutely no control - the weather.
"Today, it's a mud hole," he said Tuesday of the Hawley site, where a
temporary stop work order had been issued due to several days' rain.
In addition, this weekend is supposed to turn very cold, well below freezing,
he said.
"Concrete isn't supposed to freeze. We're using protective blankets wherever
possible," he said.
The cement will be shrouded in plastic, he added, to give it time to cure or
set up.
