Date: Fri 22-Mar-1996
Date: Fri 22-Mar-1996
Publication: Bee
Author: KAAREN
Quick Words:
railroad-bridge-Church-Hill
Full Text:
w/photo: Planning Proceeds For New Railway Bridge
B Y K AAREN V ALENTA
Representatives of the State Department of Transportation's engineering office
met with town officials this week review the state's plans for the replacement
of the railroad bridge over Church Hill Road.
Tim Gaffey, DOT project manager, said there will be a public information
meeting "in about a month" to show the plan to interested residents and answer
their questions. An artist's rendering of the bridge will be done by the DOT's
graphic design department for the meeting to give residents an idea of what
the bridge will look like.
If everything proceeds as planned, the design will be completed in July, the
project will go out to bid in December, and the construction will be done next
year, Mr Gaffey said. A preliminary estimate of the cost is $2.5 million, 80
percent of which will be paid by federal transportation funds and 20 percent
by the state.
The new bridge will be higher and wider, increasing the vertical and
horizontal clearance underneath. The state code specifies a minimum height
clearance underneath of 14-feet, 6 inches; the new bridge, as planned, has a
clearance of 14-feet, 10 inches. The existing bridge clearance is 12-feet, 7
inches, a tight squeeze for many trucks and an impossibility for most
tractor-trailers.
"We will be dramatically increasing the length of the span - to about 102 feet
- so that it can accommodate four lanes (of traffic) underneath," Mr Gaffey
said. "We won't be doing anything with the road. But we wanted to widen the
clearance and set the abutments back far enough so that if 25 years from now
Route 6 needs to be widened, a new bridge won't have to be built."
Although discussions are still being held with the Housatonic Valley Railroad,
which owns the bridge, the plan is to relocate the existing bridge about five
feet to the southwest so that rail traffic can continue while the new "through
girder" steel bridge is being built. The new bridge will be built about 16
feet to the northeast, Mr Gaffey said.
The HVR bought the bridge from Conrail several years ago and had no intention
of replacing it. The DOT decided to do the project with federal and state
funds because of the problems with the underpass that affected truck traffic
on the state road.
Once the bridge is built, it will be turned over to the railroad for
maintenance. Because of this, Mr Gaffey said the DOT is planning a galvanized
and metalized bridge that will be coated with a clear sealer "which ideally
will give 50 maintenance-free years."
First Selectman Bob Cascella said the town wants to be sure that whatever is
used will be easy to clean because the bridge has a special attraction for
graffiti artists. He also asked about the time of day that the construction
will be done and how it will affect traffic.
Keith Hall, DOT bridge designer, said Church Hill Road will have to be closed
when the first two bridge girders are swung into place, but generally efforts
will be made to keep the road open. Work will be done during daylight hours.
Public Works Director Fred Hurley said the construction of the bridge will not
interfere with the town's sewer project because the sewer main will be
installed down the center of the street this summer. The sewer work will be
done during the night, he said.
Mr Cascella said there are sight-line problems because of driveways and access
roads close to both sides of the existing bridge. This problem should be
alleviated, Mr Hall said, when the clearance is enlarged.
Mr Gaffey said the DOT may need to acquire some temporary rights from adjacent
landowners to hold equipment and materials during the bridge construction
process. It will take "about one season" to construct the bridge, he said.
Others who attended the meeting in the conference room at Town Hall South
included Tony Wamuo, project engineer for the DOT's highway section, Town
Engineer Ron Bolmer, Conservation Director David Thompson, John Whitten of
Fuss & O'Neill, the firm which is doing the town's sewer project, and Police
Lt David Lydem, who is in charge of the police department's traffic unit.
Mr Gaffey and other DOT representatives will meet with Mr Cascella again next
week to discuss the planned bypass road through Fairfield Hills.
