Date: Fri 10-Nov-1995
Date: Fri 10-Nov-1995
Publication: Bee
Author: ANDYG
Quick Words:
sewers-Alagna-treatment
Full Text:
Sewer Completion Date Slips Back Again
B Y A NDREW G OROSKO
Like many public works projects, the completion date for the town's sewer
system has receded into the future as unanticipated construction delays have
cropped up.
The projected completion date for the sewer system is now October 1997,
according to Peter Alagna, chairman of the town's Water Pollution Control
Authority (WPCA), the muncipal agency charged with overseeing the construction
and eventual opperation of the $30.4 million sanitary sewer system.
Earlier on in the project, WPCA members had projected a July 1997 completion
date. Earlier yet, they had hoped the work would be done by early 1997. Even
earlier in the project, WPCA members projected that the work would be
completed by the end of 1996.
But various factors, chief among them delays caused by archaeological research
at the sewage treatment plant site, have pushed back the completion date,
according to Mr Alagna.
"The archaeological work has been the main source of the delay... The layout
of the treatment plant had to be rearranged... Some areas simply can't be
touched," Mr Alagna said of areas at the plant site which have been designated
as "off limits" for construction by archaeologists because those areas hold
artifacts of potential archaeological significance.
Earlier this year, archaeologists affiliated with the University of
Connecticut at Storrs determined which areas shouldn't be disturbed.
Approximately $500,000 worth of state-funded archaeological research has been
done in connection with the sewer system.
The archaeologists' findings resulted in a redesign of the treatment plant
which pushed up sewer project costs. The treatment plant's $8.5 million cost
represents about 28 percent of the sewering project's construction costs.
Another factor which has contributed to delays in sewer system completion was
the protracted negotiations between the town and state over treatment plant
construction, Mr Alagna said.
The plant will have a sewage treatment capacity of almost 1 million gallons
per day. The town will have about one-third of that amount reserved for its
use, with the state having the remaining capacity.
"We're fairly confident of this new date," Mr Alagna said of the projected
October 1997 completion date for the sewer system. Construction on the system
began in November 1994.
After the system is complete, the town will then issue an order to property
owners with access to sewers to connect to the sewer system, according to
Peter Grose, the sewering project director for the town's consulting
engineers, Fuss and O'Neill, Inc.
Mr Alagna said he expects the town will give property owners several months
after construction is complete to connect their houses and businesses to the
sewer system. Because there will be only a limited number of contractors able
to work on connecting buildings to the sewer system, Mr Alagna said he doesn't
expect all sections of town served by the sewer system to connect to it
simultaneously.
The town doesn't yet have a target date for all buildings in the sewer
district being connected to the sewer system, Mr Alagna said.
Property owners will be acting independentlty of the town when they make plans
to connect to the system, he said. The out-of-pocket costs for sewer hookups
will be borne solely by property owners.
Unlike public sewer lines which are publicly owned whether they are on public
property or on private property which has a town sewer easement, the sewer
hookup lines which connect buildings to the sewer system are privately owned.
The town plans to prepare a list of state-licensed contractors who are
qaulified to connect buildings to the sewer system. Such contractors are known
as drainlayers.
After the sewage treatment plant is complete, the town will be able to treat
wastewater that is discharged by the state's facilities at Fairfield Hills,
thus helping the town to correct any technical problems with the sewage plant
before town sewage is discharged into it, Mr Alagna said.
The town is under a state pollution abatement order to rectify longstanding
groundwater pollution problems posed by failing septic systems at Taunton Pond
North, The Borough, and Sandy Hook Center. A sewer system is considered a
permanent solution to the pollution problems in those areas.
