Date: Fri 04-Oct-1996
Date: Fri 04-Oct-1996
Publication: Bee
Author: ANDREA
Quick Words:
library-Booth-asbestos-project
Full Text:
with cut: Tests Find Unacceptable Levels Of Asbestos At The Library.
B Y A NDREA Z IMMERMANN
Samples of dust particles taken last week inside the Cyrenius Booth Library
have been found to contain levels of asbestos that exceed federal EPA
standards and actions levels established by governmental health agencies,
according to First Selectman Bob Cascella.
"We are awaiting the final report [from the state]," Mr Cascella said Thursday
morning. "All we know is that quantities of asbestos were found that exceed
the legal limits. It's throughout the library, but not in every room. The
amount is unknown yet but we will have to do abatement."
Last week, dust on all floors of the library was sampled and tested for
asbestos and lead by Hygenix of Stamford. Preliminary tests indicated no
presence of the hazardous materials and others showed detectable amounts below
the 1 percent action level. But the detailed tests performed last week
indicated unacceptable levels of asbestos.
Mr Cascella said the report from the state will outline what is wrong and the
methods of abatement. Public Works Director Fred Hurley and Frank Krasnickas,
chairman of the Public Building and Site Commission, will solicit bids on the
project and make their recommendation to the first selectman. "Ben Spragg and
I are the purchasing authority, and we will hire the abatement contractor,"
said Mr Cascella. "We hope to have one on board by the end of next week."
Depending on the extent and levels of asbestos found, abatement could cost
$100,000 or more, according to Mr Cascella. The clean-up will be paid for with
the library project's contingency funds and asbestos abatement budget. "If
it's deemed there may have been negligence on someone's part, we can look,
possibly, to recoup the funds."
This does not necessarily mean litigation, he added.
Occupational Health and Safety Administration (OSHA) and the state Department
of Public Health first visited the site after a construction worker filed an
anonymous complaint. The agencies may hand out violiations if they determine
work was done improperly.
Once abatement is complete, the potential health risks will be removed,
according to Health District Director Mark Cooper. The asbestos was disturbed
when crews worked on renovations to the existing building, and the health risk
to them is low because exposure was not long-term, said the director.
"The studies are showing Asbestosis results from very high exposure over a
long period of time. And the type of situation we have at the library just
doesn't fall into that category," said Mr Cooper. "That's not to say we
shouldn't have some level of concern and that it shouldn't be cleaned-up."
Asbestos is a fine mineral fiber that has a physical presence and does not
leave a residue once removed with a special HEPA-Vac vacuum, said the health
district director. Any surface or object that has asbestos could be vacuumed
to abate the problem and remove any future health risk, he added.
Until the hazardous material is cleaned out of the building, renovation work
inside the library will be postponed. Full-time library staff will continue to
work at the site of the former A&P in the Queen Street Shopping Center,
discharging books placed in the book drop, working on Genaeology Room
materials, developing pamphlets for the different departments that will be in
the expanded library facility, planning fundraising activities for the
addition, ordering books, and answering patrons' calls. Part-time employees
are not working in the temporary space, which has been donated by property
owner Joseph Kasper.
Construction workers have three to four weeks' worth of work left to do in the
library after the asbestos abatement is complete. If the building is to be
closed for two more months, the Library Board of Trustees will explore the
possibility of opening the temporary location to the public and lending out
materials returned in the book drop.
