with cut: Report Due On Library Progress
The Board of Selectmen will receive another full report on the construction
progress of the $4.1 million addition to the Cyrenius Booth Library January
27.
Architect Bruce Tuthill of Tuthill Architects in Avon and Public Building
Committee chairman Frank Krasnickas are expected to make presentations at the
meeting.
"Hopefully it will be better than the last report we received (in December),"
First Selectman Bob Cascella said at Wednesday's Legislative Council meeting.
Last month, Mr Krasnickas reported a lack of progress with the job, as well as
insufficient planning and manpower and overall safety concerns.
Nevertheless, Friends of the Library Trustees has promised that the project
will be done within its 14-month window and at or below budget.