Library Project Concrete Contractor Replaced
The concrete contractor hired for the Booth Library Expansion Project has been
replaced due to "inadequate" work, according to Frank Krasnickas, Chairman of
Newtown's Public Building And Site Commission.
At the May 28 meeting of the commission, it was reported that the quality of
the footings poured by subcontractor H&H Construction was "acceptable but not
top quality." Forms had to be redone by the general contractor's workers, said
Mr Krasnickas. Some of the forms not readily visible were defective because
the supplementary plywood used was not properly reinforced, he said. This
resulted in bowing of the brick shelf above the foundation wall.
"The general contractor's workers are now chipping the excess concrete away. A
new subcontractor for concrete has been hired and will start next week," said
Mr Krasnickas. The general contractor for the library project, Building
Technologies Inc, had hired H&H Construction.
Although the problem has caused delays in the footing and foundation work, the
over all project is not behind schedule because the steel is not scheduled to
be delivered until the end of June or first week in July. "And the steel is
pacing the project," said Mr Krasnickas.