Date: Fri 25-Oct-1996
Date: Fri 25-Oct-1996
Publication: Bee
Author: ANDREA
Quick Words:
Booth-Library-asbestos
Full Text:
Firm Selected For Library Asbestos Work
B Y A NDREA Z IMMERMANN
Petco Insulation Company, an asbestos abatement contractor in West Haven, has
won the bid to remove the hazardous material detected in the 64-year-old
Cyrenius Booth Library building. It was scheduled to begin work October 24.
The entire clean-up should take about four weeks, according to Director of
Public Works Fred Hurley, who is coordinating the abatement.
Petco's base cost for the decontamination and abatement is $42,690 and
includes excavation of materials in the yard that need to be removed, as well
as efforts to minimize any decontamination that might occur from the
additional demolition work that is part of general construction.
Of the six contractors who bid, Acmat of New Britain was the second lowest at
$81,500; the highest bid on the project was $98,850.
"We really did do very well by casting a wide net," said Mr Hurley. Before
recommending Petco to do the job, the director of public works interviewed a
company representative to ensure he understood exactly what needed to be done.
"It was more like a pre-construction meeting. We went over everything... The
other people at the interview were Peter Cook from Hygenix, Library Director
Janet Woycik, Frank Krasnickas from the Building Committee, and Ed Callo who
is clerk of the works for the [library expansion] project."
Mrs Woycik expressed concern about the books being removed from the building
in some sort of order. It was agreed that the library will need to provide
staff to direct removal of materials, said Mr Hurley.
"This company has done [abatement at] libraries before and the others had not.
And they really did seem to understand what was involved in moving the books,"
said Mr Hurley. "They are also a call-contractor for the state's Department of
Health, so clearly they are acceptable for the state. Petco is one of the
older abatement contractors in the state; they've been in this field for over
12 years. We have a pretty good comfort level with them [after discussing the
specifications]."
The first week of abatement work will be concentrated in the building's
mechanical spaces. After the rooms are sealed off, construction contractors
will be able to enter those areas and continue work, said Mr Hurley. At that
time, BTI Construction will work in the boiler room to provide heat for the
building as soon as possible.
