Date: Fri 01-May-1998
Date: Fri 01-May-1998
Publication: Bee
Author: ANDYG
Quick Words:
Kennedy-Electrical-lawsuit
Full Text:
Electrical Contractor Sues Town Over Work At The High School
PAGE ONE
B Y A NDREW G OROSKO
An electrical contracting corporation is suing the town and two individual
members of the Public Building and Site Commission, claiming that it did not
receive full payment for work it did in upgrading Newtown High School and
helping build the school's new wing.
In a lawsuit filed April 24 in Litchfield Superior Court, Kennedy Electrical
Contractors, Inc, (KEC) of Torrington states it was hired on June 27, 1996,
following its submission of a competitive bid. KEC entered into a contract
with the town to do the electrical work for a project known as "Additions,
Modification and Code Update to The Newtown High School, State Project No.
097-099."
According to the lawsuit, the original contract price for the electrical work
was $2,335,180. After construction changes and approved extra work orders were
made, the adjusted contract price became $2,608,548, it states.
Scheduling for the project required KEC to start work on July 1, 1996, and to
complete it on or before December 1, 1997, it adds.
O&G Industries, Inc, of Torrington was the construction manager on the project
and Kaestle Boos Associates, Inc, of New Britain was the architect. KEC's work
contract with the town provided that O&G and Kaestle Boos were obligated to
review and approve KEC's payments for work properly done, to certify KEC's
applications for payment by the town, and to process those payments, according
KEC's lawsuit against the town.
Despite the town's failure to provide KEC with timely access to the site so it
could do its work, KEC finished all its work on time, the suit states.
According to the lawsuit, starting in January and February of 1998, O&G and
Kaestle Boos failed and refused to properly submit and process KEC's
applications for payment. Consequently, KEC has not been fully paid for its
completed work, the suit alleges. KEC claims it is owed approximately $182,000
by the town.
The town and its agents have thus breached KEC's contract, according to the
suit.
In a second count, KEC alleges the town acted arbitrarily, capriciously and
with destructive intent and malice toward KEC and sought to harm KEC because
it is "an open shop non-union contractor." The lawsuit adds the town
selectively and intentionally paid other contractors on the project that had
union affiliations.
In a third count, the lawsuit names Anthony W. DeCarlo of 98 High Rock Road,
Sandy Hook, and John J. Lipusz of 11 Wildcatt Road, both of whom are members
of the Public Building and Site Commission, as individual defendants in the
civil case.
The suit states Messrs DeCarlo and Lipusz are both trade union members and
have repeatedly and without justification demonstrated unwarranted animosity
toward KEC solely because KEC is a non-union contractor.
Messrs DeCarlo and Lipusz illegally used their positions to wrongfully
interfere with KEC's contractual relations with the town by repeatedly
ordering the town's agents to delay, table, or set aside KEC's legitimate
requests for payment, the suit adds. The suit alleges the defendants' acts and
omissions have been malicious and intentional and intended to harm KEC.
In a fourth count, the plaintiff alleges the defendants' actions were unfair,
deceptive, intentional and malicious.
A fifth count alleges KEC was forced to work on the project out of sequence
and in a shorter time period than it reasonably anticipated. Thus, KEC was
forced to increase its crew sizes and the hours worked by its crews, causing
the company to expend almost 60 percent more labor hours at an increased cost
to it of $506,546, the suit states. The contractor is seeking to recoup these
losses from the town through the lawsuit.
Through the lawsuit, the electrical contractor seeks money damages, interest
and costs; exemplary damages under the second and third counts; attorney fees
and tripled damages as per the fourth count, and other relief deemed proper by
the court.
Attorney Steven B. Kaplan of the law firm Michelson, Kane, Royster and Barger,
P.C. of Hartford represents KEC in the lawsuit.
Town Response
First Selectman Herbert Rosenthal said Wednesday, "I ordered payment when the
(Public Site and Buildings Commission) had denied payment on a couple of the
bills." In those bills, KEC sought overtime payments, he said.
Mr Rosenthal said he intervened in the matter on behalf of KEC.
The first selectman said he needed to review the minutes of the commission's
meetings to gain a deeper sense of what occurred.
If Messrs DeCarlo and Lipusz gave KEC a hard time, it would be a very serious
matter, Mr Rosenthal said.
Members of the commission are appointed by the selectmen and also can be
removed by the selectmen, Mr Rosenthal said.
"I don't want to admit liability in this lawsuit in any manner," he said.
He termed the language of the lawsuit "intense."
On Thursday, after having read some recent minutes of the Public Building and
Site Commission, Mr Rosenthal said, that without regard to the pending
lawsuit, he was very disappointed to read what he termed the "irresponsible
and intemperate" comments of Mr Lipusz. The first selectman said Mr Lipusz had
characterized workmanship at the high school project as "horrible" and also
had attacked the school board, blaming it for problems with the school
expansion project.
Mr Rosenthal said the lawsuit will be referred to town lawyers for review. The
town has a May 12 court appearance date in the matter.
