Date: Fri 11-Oct-1996
Date: Fri 11-Oct-1996
Publication: Bee
Author: ANDREA
Quick Words:
library-asbestos-Booth
Full Text:
Town Awaits Approval Of Asbestos Clean-Up Plan For Library
B Y A NDREA Z IMMERMANN
Town and health district officials await approval by the state Department of
Public Health of an asbestos abatement plan for the interior of the Cyrenius
Booth Library.
The plan was recommended this week by HYGENIX Inc of Stamford, which found
unacceptable levels of asbestos at the site. The company tested for lead and
asbestos within the existing library building, and is now sampling for
asbestos outside the building.
Twenty samples of construction material within the building were tested for
asbestos the last week in September. In addition to the
asbestos-containing-materials (ACMs) previously identified by Mystic Air
Quality Consultants, the company reported that ceiling tile glue-dot and roof
flashing material also contained levels of asbestos that exceed action levels
established by the EPA and state Department of Public Health.
After the September 24 site inspection by Hygenix, the company reported:
"Throughout much of the library, books, shelving, furniture and office
equipment was still in place, and covered loosely with plastic drop cloths. In
many spots, especially areas near recently-cut openings in the plaster walls
and ceilings, large amounts of construction dust and debris covered the
exposed surfaces. The abatement recommended by Robert Brown, director of
industrial hygiene for HYGENIX, assumes "that all contents of the library will
require decontamination."
Mr Brown outlined a five-step abatement process "based on the excessive level
of asbestos dust throught the library, and presences of lead dust at limited
locations within the library." The clean-up would utilize a HEPA vacuum
system, which is designed to remove such hazardous material.
After doing preliminary work to establish a decontaminated "Clean Holding
Area," the report recommends the following:
Working one at a time, wet wipe and/or HEPA vacuum all movable items, and pass
them through a series of air locks into the Clean Holding Area.
As the Clean Holding Room is filled with cleaned items, retest the room for
airborne asbestos by [Transmission Electron Microscopy] (TEM). If test results
are acceptable, remove the materials to a storage area outside the library.
As each library area is emptied, clean all exposed surfaces by HEPA vacuuming
and washing. Document adequacy of cleaning by performing aggressive TEM
clearance of each vacated area.
After documenting adequate cleaning of vacated area, seal the room and repeat
the process in the next area...
Do not remove containment barriers and HEPA ventilation systems until the
final visual inspections of all library areas is satisfactory and clearance
air samples demonstrate airborne fiber levels less than 70 asbestos
structures/mm2 average in all building areas.
Eight of the samples taken by HYGENIX showed lead content less than the
maximum level permitted for reoccupancy. "The generally low lead content in
wipe samples, despite the thick layer of dust, can be related to the small
number of plaster surfaces with lead-based paint," stated the report.
One sample, recorded on a concrete floor on the lower level was elevated, and
theorized to be from a residual of epoxy paint floor sealant, not from
construction disturbance.
Complete Abatement Plan
Town officials expect the DEP to approve a complete abatement plan by the
beginning of next week; they hope to have an abatement contractor hired by the
end of the week, according to Public Works Director Fred Hurley, who is
coordinating the clean-up. The plan would include forthcoming proposals that
address the potential disturbance of asbestos in the remaining construction
work, and possible contamination outside the building.
The initial clean-up, which will abate the asbestos material already disturbed
inside the library, will probably take a couple of weeks, according to Mr
Hurley. "The abatement contractor will be working inside the library with a
staging area outside with trailers. The library will be vacated from top to
bottom," he said.
First Selectman Bob Cascella said that once the furniture, equipment, and
books are removed from the library, construction crews will go in and complete
the work they have postponed because of the problem with hazardous material.
Crews have concentrated their effort on the addition while the building has
been closed, so Mr Cascella believes the project completion date may not be
far off schedule.
"We are moving on this thing about as fast as we can. It's become a top
priority," said Mr Cascella, who, along with Finance Directpr Benjamin Spragg,
will authorize contingency funds to pay for the clean-up. "We're taking this a
piece at a time - we have to for obvious reasons." He said "it's just too soon
to tell" when the library will reopen to the public.
"We're getting full cooperation from town agencies and the contractors, and
keep plugging along," he said.
Mark Cooper, Director of the Newtown Health District, said they have already
acted on the first of HYGENIX' recommendations by posting a sign at the
library restricting access to personnel trained in and outfitted for asbestos
removal.
The Library Board of Trustees is considering the option to open a temporary
location so the public can check out library materials returned to the book
drop and decontaminated through abatement.
