Date: Fri 09-Feb-1996
Date: Fri 09-Feb-1996
Publication: Bee
Author: ANDREA
Quick Words:
library-Baumer-lawsuit
Full Text:
PAGE ONE: Court Denies Request For Library Restraining Order
B Y A NDREA Z IMMERMANN
After four hours of testimony ending on February 7, Judge Howard J. Moraghan
denied Edwin Baumer's request for a temporary restraining order which would
have halted the approved library expansion project until all of his lawsuits
relating to the matter were settled.
Mr Baumer and his wife, Jean, who live next door to the library, initiated two
lawsuits involving the 4.1 million dollar project last summer.
Randall Carreira, the attorney representing the plaintiffs, tried to sway the
judge by having Mr Baumer explain how the 22,000 sq ft library addition would
adversely affect his lifestyle, and by grilling project coordinators, and
library and town officials on how the project evolved.
Mr Baumer, 78, who sat by himself on one side of the courtroom, testified that
the addition would destroy his "environment, privacy, and property value...
[Activities at the library] tend to restrict use of my property because I
constantly seem to see people looking in the direction of my property," he
said. "This is intensifying as more people use [the library]."
Another issue that vexes Mr Baumer is "illegal parking all over Main Street."
And during the library's annual Labor Day book sale, Mr Baumer said people
"tresspass" on his property, approaching him to ask questions regarding the
architecture of his 1823 wood frame house.
Mr Carreira contends zoning regulations were changed to accommodate the design
of the library. In an attempt to prove his points, the attorney posed detailed
questions to library architect Bruce Tuthill, First Selectman Bob Cascella,
Library Director Janet Woycik, Borough Zoning Officer Jean St Jean, Vice
President of Library Board of Trustees Kathy Geckle.
The three defense attorneys called and cross-examined the witnesses to refute
this. Attorney Don Mitchell represented the Borough and the Borough Zoning
Commission and led the defense; Sutherland Denlinger and David Grogins both
represented the library trustees.
The team also tried to establish the increased cost that might occur if the
library project were delayed. Contractor Keith Crumb testified that
construction costs would probably increase five percent, or a total of
$150-$160,000, and administrative costs would be an additional $140-$200,000;
the architect gave the breakdown of his projected increased cost of $32,000
for a six-month delay and $44,000 for a 12-month delay; and the library
director explained building must begin by August 2 for them to meet the
requirements to receive the $350,000 state grant which was awarded for the
project.
Before offering his decision, Judge Moraghan said it may have been established
the plaintiff might suffer "irreparable annoyance, and irreparable
frustration" at expansion of the neighboring building, but there was "nothing
before the court" to show irreparable damage.
The term "irreparable" translates to mean "permanent." Construction of a
building, such as the library, is not "permanent" said the judge because if Mr
Baumer wins his pending appeals and the court so orders, the library would be
taken down "brick by brick, square foot by square foot."
Two points of law considered by the judge were "relative harm," and if there
was adequate remedy in law. "What we had today was an equitable remedy," said
Mr Mitchell, who felt the judge's determination was "the appropriate" result.
"If [Mr Baumer's] property is reduced in value, that is compensable in
dollars. If there's annoyance, if he is temporarily damaged during
construction - that is remedied through dollars. His 'remedies' are his
appeals...and money damages."
To prove "relative harm" the court has to find that the harm resulting to the
applicant from no injunction far outweighs the damage to the respondant to an
injunction, said Mr Mitchell. That is why there was testimony on increased
costs, he added.
"There is no basis for the injunction of a restraining order," the judge
decreed.
Hugs, handshakes, and a lot of smiles were shared by project coordinators and
library supporters. "I'm ecstatic - we go to work this time," said Mrs Woycik,
running through a list of possible areas to start construction. "We're going
to get a foundation permit and get started ASAP," she said.
"Our opponent had his day in court," said Mrs Geckle. "We went through the
justice system and the facts won."
"Nobody likes to lose; I wasn't jumping for joy," said Mr Carreira, in
response to the determination. "You go on for another day, another time - you
regroup...We still have the actions that are pending."
Although he decline to make an official comment after the judge's decision, Mr
Baumer was heard saying to his attorney, Randall Carreira, "We tried."
