Date: Fri 26-Apr-1996
Date: Fri 26-Apr-1996
Publication: Bee
Author: KAAREN
Quick Words:
Church-Hill-railroad-bridge
Full Text:
Designers Fill In Details Of New Church Hill Rail Bridge
B Y K AAREN V ALENTA
Only a handful of people - mostly town officials - attended the public
informational meeting held in the high school auditorium last Thursday evening
on the state's plans for the replacement of the railroad bridge over Church
Hill Road.
The DOT representatives who attended the meeting - Tim Gaffey, the project
manager; Keith Hall, the bridge designer, and engineers Tony Wamuo and Mike
Marzi - brought a computer-generated photo of what the new $2.5 million bridge
will look like and preliminary drawings showing construction plans.
Mr Gaffey said the final bridge design must be approved by the Federal Highway
Administration because the project is being financed 80 percent by the federal
government and 20 percent by the state. No local funding is required.
The existing bridge, built about 1929, is a 35-foot, 6-inch long "through
girder" style bridge that carries one track of the Danbury Terminal Railroad
Company. The clearance underneath is only 12-feet, 7-inches, an impossible
squeeze for most tractor-trailer trucks. There were 24 reported instances of
trucks striking the bridge between 1993 and 1995, Mr Gaffey said.
The new through girder steel bridge also will carry only one track but it will
be higher with a vertical clearance underneath of at least 14-feet, 6-inches.
"Ideally, new bridges have 16 feet of clearance, but we are limited by the
existing rail," Mr Gaffey said. According to state law, trucks can be no more
than 13 feet, 6 inches high.
Mr Gaffey said that if everything proceeds as planned, the bridge design will
be completed in July, the project will go out to bid in December and the
construction will begin next spring.
During the construction period the existing bridge will be moved five feet to
the west (toward the flagpole) so that rail traffic can continue. A new
bridge, 102-feet long, will then will be built about 16 feet to the east
(toward Wire Road) on an angle between the abutments.
The bridge supports will be moved to create an opening that could eventually
accommodate four lanes of traffic, but Mr Gaffey stressed that there are no
plans at this time to widen the road. The roadbed under the bridge will remain
at 23 feet: two 10-foot traffic lanes and 1«-foot shoulders. The town plans to
install sewers in the middle of the road this summer.
Once the bridge is built, it may be turned over to the railroad for
maintenance. Because of this, Mr Hall said the DOT is planning a galvanized
and metalized bridge which will be coated with a clear sealer which ideally
will give 30 to 50 maintenance-free years and will be relatively easy to clean
if graffiti is applied.
Most of the construction work will be done between 9 pm and 6 am with
alternating traffic lanes open and a flagman on duty. However, the road will
have to be closed "for about an hour" when each of the two 90,000-lb beams are
lifted into place, Mr Gaffey said.
He said the DOT estimated that 10,000 to 12,000 vehicles go under the bridge
each day. "That's a lot of vehicles for a two-lane road," he said.
The existing stairs and crumbling brick wall adjacent to the bridge will be
removed and not replaced. Four utility poles will be relocated. About a dozen
trees will be removed. Replacement landscaping will include spring-flowering
shadblow sweetberry trees and burning bushes, which have red berries in the
fall.
The five-foot wide concrete sidewalk under the bridge will be replaced as far
to the east and west as required and the road under the bridge will be
resurfaced to a maximum of about 100-feet each way from the center of the
bridge. There also may be a fence along each end of the bridge to discourage
trespassers.
