Date: Fri 03-Oct-1997
Date: Fri 03-Oct-1997
Publication: Bee
Author: STEVEB
Quick Words:
high-school-contingency-fund
Full Text:
High School Construction Contingency Fund Runs Low
BY STEVE BIGHAM
The Newtown High School contingency fund appears to be running on empty.
Last month, the Board of Education was informed that about half of the
project's million-dollar emergency fund still remained. However, several
surprisingly large bills arrived in the mail recently, sending contingency
expenses through the roof. Two of those bills have put an additional $330,000
dent in the fund, which is set up to cover unforeseen costs on large projects.
Another $660,000 has already been used from the fund to cover change orders at
the site. Some of them are still pending.
"My understanding is we'll have enough to finish the job, but we're monitoring
it very closely," Board of Education Chairman Herb Rosenthal told the
Legislative Council's finance committee Wednesday night.
The school system recently received an invoice for moving and storage
totalling $225,000, a huge bill considering the school had only set aside
$40,000 for moving and storage. During the project, school officials said they
were forced to find an outside source to store furniture and other school
materials. Originally, the plans called for storing the material in the high
school's new addition. However, it was not completed in time and requests to
store the material at Town Hall South were denied.
The school was surprised when a second bill, totalling $180,000, arrived for
dumpster usage. This bill was especially surprising since only $30,000 was
budgeted for dumpsters. This was an apparent error made by the project's
general contractor, O&G Industries.
"How O&G could have estimated $30,000 and come out to where it did, I don't
know," Mr Rosenthal said.
Earlier this week, the school system's business manager, John Torok, was
visiting area warehouses trying to figure out why the bills were so high.
"Unfortunately, these bills just start coming in," he said. The amount of
money still remaining in contingency is still being determined, he said.
Council chairman Pierre Rochman said he was baffled at how the available
contingency funds could drop from $500,000 down to near zero so quickly.
"Unless you're using a crystal ball, it's hard to determine what all the costs
will be," Mr Torok said. "You try to give it your best estimate."
At Hawley School, $40,000 in contingency funds remain from the original
$150,000 set aside.
None of the $80,000 set aside for contingency during the Head O' Meadow School
roof replacement was used.
The high school project is slated to be complete by November 24.
