Date: Fri 08-Aug-1997
Date: Fri 08-Aug-1997
Publication: Bee
Author: ANDYG
Quick Words:
DOT-Bypass-Wasserman-Sullivan
Full Text:
DOT Commission Explains Reasons For Bypass Delay
BY ANDREW GOROSKO
The commissioner of the state Department of Transportation (DOT) has explained
the reasons for delays in getting the Fairfield Hills bypass road project
underway.
In a letter to State Rep Julia Wasserman, DOT Commissioner James Sullivan
writes, "Several issues have delayed the contractor's efforts in moving the
project at a faster pace. These issues include environmental permitting
problems at the bridge site, delays in Department of Environmental Protection
soil testing for the wetland mitigation area, and undocumented underground
utilities in several areas. The contractor is making efforts to minimize
delays. I am confident that they will resolve the outstanding issues in a
timely manner."
Mr Sullivan's August 5 letter came in response to Mrs Wasserman's July 15
letter inquiring why work isn't underway on the bypass, which is intended to
alleviate traffic congestion in the town center.
In June, workmen began preliminary construction on the bypass road planned to
link Route 25 to Exit 11 of Interstate 84, and to Route 34 to improve local
east/west traffic flow.
Construction is slated to resume soon, David Anderson, DOT's chief inspector
on the project, has said.
The completion date for the bypass road has been moved back to September 3,
1999. In the past, DOT officials had said the project would be completed by
the end of 1998.
Traffic will continue passing over Mile Hill Road while the bypass road
project is under construction.
It's expected that Dayton Construction Company of Watertown will complete
construction of a bridge over the Pootatuck River by the end of 1997, Mr
Sullivan wrote.
"Once this bridge is completed, the contractor will use the bridge during the
construction [of the remainder of the project]. The contractor anticipates
that they will complete most of the [remainder] of the contract by the end of
1998. The only work that may remain would be the final course of pavement,
shoulder work, landscaping and general clean-up," Mr Sullivan wrote.
In a response to Mr Sullivan's letter, Mrs Wasserman wrote, "I would hope that
aside from potential unforeseen minor field changes there be no additional
delays."
Mrs Wasserman also asks for clarification on whether the matters which have
delayed the start of the project will continue to cause delays. She has
expressed unhappiness that the official completion date of the project is
September 3, 1999.
The overall cost of the project is estimated at $4 million, including
construction and design expenses.
Advanced erosion control measures will be used during bypass road
construction. Special contamination traps will be installed because the area
lies above the Pootatuck aquifer. The bypass road project is environmentally
significant because it is unusual to build a major connector road in a place
containing an area's designated sole source aquifer.
A combination of state and federal funds will cover project costs. The new
road will bypass the core campus of Fairfield Hills. The road will extend from
the intersection of Mile Hill Road South and Mile Hill Road to the area where
Mile Hill Road intersects with Oakview Road.
A 1991 agreement, which resolved a lawsuit filed by the town against the state
over the state's construction of Garner Correctional Institution, provided, in
part, that the state build a bypass road across the Fairfield Hills grounds.
