Newtown Village Developers Look Ahead To P&Z Review
BY ANDREW GOROSKO
The developers of Newtown Village met with town officials Wednesday seeking to
learn how they can refine their proposal to gain Planning and Zoning
Commission (P&Z) approval for the 102-house project.
Issues raised by town officials included traffic, wastewater disposal, water
supply and fire protection.
D&H Homes, LLC, of New Milford, and Fairfield 2000 Homes, Corp, of Stamford,
want approval to build 102 houses, 25 of which would be designated as
"affordable." The 32-acre development site is a former sand-and-gravel mine in
Sandy Hook in the area bounded by Berkshire Road, Bishop Circle, Philo Curtis
Road, and the eastbound on-ramp at Exit 11 of Interstate 84.
In the face of strong opposition from neighbors, the Conservation Commission
on Monday granted a wetlands construction license for Newtown Village. (See
related story.)
The developers are now formulating an application for P&Z review.
Sandy Hook Volunteer Fire and Rescue Company Chief Bill Halstead pointed out
that traffic is very heavy on the section of Route 34 between Toddy Hill Road
and Mile Hill Road during the rush hours of 7 to 9 am and 4 to 6 pm. The
developers plan to build the entrance/exit to Newtown Village on that section
of Route 34.
The fire chief said rush hour traffic there makes for "a very hectic
situation," and asked what effect the presence of 102-house development would
have on traffic in the area.
Michael Petti, an engineer for Stearns & Wheler, Inc, of Darien, representing
the developers, said a traffic study has been done. The developers would make
physical improvements that would slightly improve traffic flow there, he said.
But, he added, "It's not reasonable to expect us to solve the [traffic]
problems on Route 34. It is reasonable to expect us not to make them worse."
Building Official Robert Brinley questioned the developers' proposal for an
emergency access road to the development leading from Philo Curtis Road. Such
emergency roads are unworkable because they typically are not maintained, he
said. He suggested the developers create a conventional road leading to Philo
Curtis Road to serve as a second entrance/exit to the property. Mr Brinley is
a deputy fire marshal.
Wastewater
Mr Petti said the developers have been discussing aspects of the project's
wastewater disposal system with the state Department of Environmental
Protection (DEP).
The developers propose building a community septic system to serve all houses
on the property. That system would include devices to "pre-treatment"
equipment to remove nitrogen from the water before it enters leaching fields.
Water Pollution Control Authority (WPCA) regulations, however, prevent
high-density developments with community septic systems from using
pre-treatment devices.
Mr Petti said the developers believe they are caught in a "catch-22" situation
because the WPCA regulation would prevent any pre-treatment of wastewater, in
effect, preventing the creation of high-density "affordable housing."
Town zoning regulations have provisions that allow the creation of affordable
housing, he pointed out. Affordable housing only becomes possible when there
are high construction densities, he said.
John Horton, a manager for D&H Homes, said the developers' first choice for
wastewater disposal would be connecting the complex to the municipal sewer
system.
A sewer line that will be extended to Newtown High School, in the vicinity of
Newtown Village, however, has been designated by the town as a "transmission
line" intended only for high school use.
Mr Petti asked how the developers' application can be made consistent with the
town's regulations.
Town Health Director Mark Cooper said the wastewater disposal issues are
matters that will have to be resolved by P&Z and the WPCA.
Water and Fire
Mr Petti said the developers would have water supplied to the housing complex
by United Water, a local privately-owned public utility company. Water would
be supplied either by an extension of United Water's water system or by having
United Water create a community water supply system on the development site by
drilling a well or wells. In either case, United Water would own the water
supply system.
The developers would prefer having United Water's system extended to the
complex, Mr Petti said.
If United Water extends its system to Newtown Village, the complex would be
served by fire hydrants for firefighting.
But if an on-site water supply is created, water storage tanks would be buried
in the complex for firefighting.
Chief Halstead told the developers, "Once you guys are gone, we still have an
obligation to protect these people and their properties... Your [housing]
density here is a lot greater than your average subdivision."
The houses would be close together and there would be a much greater chance
for fires to spread between them than in a normal subdivision, Mr Brinley
said.
A typical lot in the complex would have 65 feet of frontage and be 100 feet
deep, or cover about one-seventh of an acre. Houses would be set back 25 feet
from the street. There would at least 20 feet separating individual houses.
Mr Petti told town officials the developers will satisfy their concerns about
fire protection in the complex.
Fire Marshal George Lockwood expressed concerns about how many people would be
living in the complex when it is completed, and asked if P&Z would allow
accessory apartments to be created.
There would be a total of about 275 bedrooms in the 102 houses. The two-story
houses would range in size from 1,400 to 2,100 square feet and would be built
in six styles.
Roads in the complex would be privately owned. An owners' association would be
responsible for road maintenance and snow plowing.