Date: Fri 14-Feb-1997
Date: Fri 14-Feb-1997
Publication: Bee
Author: ANDYG
Quick Words:
sewage-treatmentplant-Whitten
Full Text:
Sewage Treatment Plant Is About Two-Thirds Done
(with photo)
BY ANDREW GOROSKO
A small army of workmen has been toiling through the winter assembling the
components of an $8 million sewage treatment plant on an eight-acre site
alongside the Pootatuck River.
When completed, the sprawling facility will cleanse the wastewater carried by
the municipal sewer system now under construction and will clean the sewage
discharged from the state-owned Fairfield Hills complex.
Workers have installed a triple box culvert across Tom Brook, allowing
vehicles to pass from the end of Commerce Road to the treatment plant site.
An administration building composed of red, brown and ivory colored concrete
blocks is being built nearest the Commerce Road entrance. A sewage filtration
building stands beside it. A massive emergency generator is positioned on a
concrete pad next to the filtration building. In the event of a power outage,
the generator will be switched on to provide power to run the plant.
The treatment plant is about two thirds complete, said John Whitten, the
senior field representative for Fuss and O'Neill, Inc, the Manchester
engineering firm which designed the sewer system for the town.
If all construction continues as planned, the town sewer system should be
complete by September. Initial wastewater flows to the treatment plant will
come from Fairfield Hills, the former state mental hospital whose largely
vacant buildings are now used only by Addiction Prevention Therapy for drug
rehabilitation and by the town for temporary office and library space. The
state will also route wastewater from Nunnawauk Meadows and Garner
Correctional Institution to the treatment plant.
Fairfield Hills has reserved two-thirds of the wastewater treatment capacity
at the million-gallon-per-day treatment plant. The town has the remainder.
The plant is laid out to allow another million gallons of treatment capacity
to be built nearby.
Two areas on the plant site have been posted as "off limits" to construction
crews because they may hold artifacts of archaeological significance.
When wastewater arrives at the treatment plant from different directions it
will be combined in a headworks building, be channeled to a series of
oxidation ditches and then exposed to ultraviolet light for cleansing. The
wastewater collected by 21 miles of town sewer lines will then enter
clarification tanks, after which it will enter the filtration building before
being discharged into a drainage channel leading to the Pootatuck River.
The treatment plant will provide tertiary wastewater treatment and include
denitrification equipment to reduce nitrogen levels in the wastewater.
"The project's going together well. Everything's going good. There was [much
time spent] planning this," Mr Whitten said.
The town plans to hire a management firm to operate the treatment plant and
possibly maintain sewer lines in the Borough, Taunton Pond North and Sandy
Hook Center.
As the treatment plant construction continues, workers are laying out
construction plans for four sewage pumping stations that are needed to move
sewage uphill from low spots on the periphery of the sewer system. The
stations will be built on Hanover Road, Glen Road, Taunton Lake Drive and
Baldwin Road.
Workmen started construction on the $34.3-million town sewer system in
November 1994.
After the sewer system is complete, the town will set a time period during
which residential and non-residential customers will be required to connect
their wastewater drains to the system. The "out of pocket" costs that sewer
users will bear to connect to the system will vary depending on the complexity
of their particular sewer hookup.
Building a municipal sewer system was discussed for decades before voters
approved bonding for the project in 1992. The system is being built to rectify
longstanding groundwater pollution caused by failing septic systems.
