Date: Fri 22-Aug-1997
Date: Fri 22-Aug-1997
Publication: Bee
Author: STEVEB
Quick Words:
schools-NHS-opening-delay
Full Text:
NHS Opening May Be Delayed
B Y S TEVE B IGHAM
The rumors floating around town could turn out to be true after all. It's
looking more and more like Newtown High School won't be ready by the first day
of school.
Summer vacation for high school students could be extended by as much as a
week.
School officials have been optimistic all along that the $26 million NHS
construction project would be completed by September 3, but this week they
began tempering that optimism with caution - a bit of frustration, as well.
"There's a chance we might open three to four days late, but I'm not going to
speculate," said Superintendent of Schools John R. Reed Tuesday. "I'm not
going to open school just to prove a point."
Town building officials have spent much of their time recently at the school,
testing alarm systems, sprinklers, emergency doors, etc. Things are moving
along quickly, but not quickly enough, they say. Teachers scheduled to arrive
for work this coming Monday morning probably won't be able to.
While school officials continue to hold out hope, the final say on when the
high school will be ready comes down to one man, Al Brinley, the town's chief
building inspector, and he doesn't think it will be done on time. On Tuesday,
he said a certificate of occupancy (CO) probably wouldn't be issued for
another two weeks.
"I think everyone that is involved in this project is concerned. They're just
a couple of weeks shy," Mr Brinley said.
Fire Marshal George Lockwood agreed.
"We've got to get these schools open somehow, but we don't see how it can be
possible," said Mr Lockwood. "They want the CO for next Monday. I doubt
they'll have it."
School officials were hoping the CO permit, required before school can start,
would be issued by next Monday. Dr Reed said teachers will need a week to
prepare before students can come in.
Workers have been putting in overtime in their efforts to complete the upper
level of the existing building. That's the area of concern. The new
74,000-square-foot wing at the school is likely to be done, and the school
will be able to get by without having access to the lobby and main office
area, but school can not open until the upstairs of the old building is
certified for occupancy.
Though school officials remain optimistic about Hawley School's $4 million
project being done by the first day, there is still the chance that it could
also face a delayed start, especially if a glitch in the new sprinkler system
is not rectified.
Dr Reed said he continues to keep the pressure on the general contractor, O&G
Industries, to get the job done. No matter when school opens, he wants to
ensure that the rapid pace of the work remains constant. Nevertheless, the
superintendent acknowledges that he has no real control over how quickly or
slowly things get done, or how "reasonable" town agencies will be in issuing
permits. He asks that parents, teachers and students keep their ears open for
any announcements as Day 1 draws near.
"We'll keep the community informed with letters, on the radio and with our
telephone chain," he said.
All other Newtown schools will open on time, even if NHS and/or Hawley do not,
Dr Reed said. The superintendent said there's no truth to the rumor that
students will have to attend school on Saturdays if there is a delay.
When the high school does finally open, sections of the school will still
remain off limits. The lobby, main office, auditorium, music area and media
center won't be done until December. Sheet rock walls will be erected at each
end of the lobby to block access to these areas.
Next Wednesday at 7 pm, the school system will air a program on Channel 21
that will focus on what high school students can expect when they arrive. For
one thing, students will not be able to enter through the main lobby area.
Instead, they'll enter the building through the doors near the area where the
old building connects with the new.
