Date: Fri 25-Apr-1997
Date: Fri 25-Apr-1997
Publication: Bee
Author: KAAREN
Quick Words:
Railroad-bridge-Church-Hill
Full Text:
Railroad Bridge Replacement Now In Doubt
B Y K AAREN V ALENTA
One year ago, on April 26, 1996, representatives of the state Department of
Transportation conducted a public informational meeting in Newtown on the
state's plans for the replacement of the railroad bridge over Church Hill
Road.
The DOT representatives - Tim Gaffey, the project manager; Keith Hall, the
bridge designer; and engineers Tony Wamuo and Mike Marzi - brought a
computer-generated photo of what the new $2.5 million bridge was expected to
look like and preliminary drawings showing construction plans.
At the time, Mr Gaffey said that if everything proceeded as planned, the
bridge design would be completed in July, 1996, the project would go out to
bid in December, 1996, and the construction would begin in spring 1997.
Instead, the project is on hold - and may not even be done, Mr Gaffey said
this week.
"The Danbury Terminal Railroad hasn't finished its track relocation plans but
we were informed that relocating a mile and a half of track would cost nearly
$1 million, rather than the $200,000 or so which we originally anticipated,"
he said. "At the same time, we did some testing of the existing abutments and
footings and the results have been leading us to the conclusion that we may
not be able to use them (to support) the temporary track."
The DOT briefly looked again at the possibility of lowering the road under the
bridge but has ruled that out, he said.
"So we're back to the choice of replacing the bridge or walking away from it,"
he said.
DOT had taken on the project to facilitate truck traffic on Church Hill Road
because it is a state highway, Route 6. Most tractor-trailer trucks are unable
to pass beneath the bridge, which stretches across the road just 12'7" above
the pavement.
"If enough traffic is siphoned off by the new bypass road through Fairfield
Hills, then a new railroad bridge might not be needed," Mr Gaffey said.
About 10,000 to 12,000 vehicles go under the railroad bridge on a typical day,
according to the DOT.
Even if the DOT does decide to proceed with the bridge, construction wouldn't
begin before next year, Mr Gaffey said.
"Certainly we wouldn't start work on the (railroad) bridge until the bypass
road is almost completed," he said. "We wouldn't want to choke off traffic on
the only two east-west roads through the center of town."
The bridge project was to be funded 90 percent by the federal government and
20 percent by the state. But Mr Gaffey said recent changes in federal programs
have raised questions about whether the money will be available.
"It doesn't look good," he said.
Mr Gaffey said he is trying to set up a meeting involving representatives of
various DOT departments - structural engineers, soils specialists, highway
designers and bridge designers - to talk about the status of the project and
the results of the tests of the abutments and footings.
Although the DOT has said that one-lane traffic will be preserved through
Fairfield Hills while work progresses on the bypass road, traffic has been
diverted off Mile Hill Road during non-rush hours during the past two weeks to
allow gas company workmen to install new pipes which cross under the road.
Dayton Construction Company of Watertown also has been on the scene setting
out surveying flags. According to the contract, the company has 18 months to
construct the 1.3 miles of new roadway and reconstruct the bridge over the
Pootatuck River.
Mr Gaffey said he was unaware that traffic has been detoured off Mile Hill
South.
"That's something which is being done by the utility companies, not by the
DOT," he said.
