Date: Fri 12-Dec-1997
Date: Fri 12-Dec-1997
Publication: Bee
Author: STEVEB
Quick Words:
high-school-project
Full Text:
NHS Project Heads To Completion In January
BY STEVE BIGHAM
The Newtown High School lobby was finally open to students and staff last
week, signaling a near completion of the school's $28-million face lift.
NHS Principal Bill Manfredonia said this week that he hopes the massive
renovation/addition will be completed by late January. When completed, it will
bear little resemblance to the troublesome old school built in 1970.
"We're coming down to the end," the principal said Tuesday.
The project began 16 months ago, soon after the town voted in favor of the
expenditure nearly 2-1. Voters also approved a smaller project at Hawley
School.
Last week, the high school suddenly grew in size as workers finally opened a
refurbished lobby area, main office, guidance department and career center.
Those areas had been closed off since the start of school in late summer.
Three weeks ago, the school's new media center, now tripled in size, was
opened to students and staff. The roomier library looks out onto a courtyard,
which divides the existing school with the school's new 73,000-square-foot
addition. The library includes institutional and distance learning classrooms,
computer work stations, stacks, reading areas and a faculty professional
library.
"It's such a pleasure to know that there's room for whatever number of
students need to be in there," Mr Manfredonia said.
The old library had just 5,500 square feet of space. The new athenaeum is a
spacious 13,000 square feet.
By next week, the school's chorus, culinary and band rooms are also expected
to open. After that, all that remains to be completed will be the technology
rooms, graphic arts and auto shop on the school's lower level.
The opening of school was delayed by a few days in September as workers rushed
to finish the 73,000-square-foot addition on the north side of the building.
Once that was completed, school was open, but many areas were off limits as
construction continued. Those areas are finally becoming accessible to
students, but it has taken more than three months and everyone was forced to
compromise.
Many of the improvements to the school can't be seen on the surface. They
include an extensive mechanical overhaul to update and replace the heating,
ventilating and air conditioning systems. A large section of the roof has also
been replaced.
The track at Bruce Jenner Stadium is still not completed, according to Mr
Manfredonia. However, he said crews will have it ready for track & field
season in the spring.
Running On Empty
This past fall, the project's $1 million contingency fund appeared to be
running on empty. However, School Business Director John Torok said he is
confident the project will not go over budget.
Several surprisingly large bills arrived in the mail this past fall, sending
contingency expenses through the roof. Two of those bills have put an
additional $330,000 dent in the fund, which is set up to cover unforeseen
costs on large projects.
"I don't think there's going to be a lot left, but I honestly don't think
we're going to run out," Mr Torok said Thursday.
Nearly $700,000 of the $1 million has already been used from the fund to cover
change orders at the site. Some of them are still pending. Also, the school
system received an invoice for moving and storage totalling $225,000 in the
fall, a huge bill considering the school had only set aside $40,000 for moving
and storage.
During the project, school officials said they were forced to find an outside
source to store furniture and other school materials. Originally, the plans
called for storing the material in the high school's new addition. However, it
was not completed in time and requests to store the material at Town Hall
South were denied by then-First Selectman Bob Cascella. The school was
surprised when a second bill, totalling $180,000, arrived for dumpster usage.
This bill was especially surprising since only $30,000 was budgeted for
dumpsters. This was an apparent error made by the project's general
contractor, O&G Industries.