Proposed Five-Year Capital Improvement Plan For Schools Unveiled
B Y D OROTHY E VANS
Superintendent of Schools John Reed and Buildings and Grounds Supervisor Dom
Posca presented the 1997/98 draft version of a five-year capital improvement
plan to the Board of Education December 3.
There were no big surprises, but the bottom line figure showing total
estimated expenditures between 1997 and 2002 was nevertheless a sobering one.
If all the proposed projects are carried out and if the estimates prove
accurate, the plan shows that a total of $2,667,000 over that five-year period
will be needed.
"This is merely a planning document and most of the items were in last year's
plan and the year before," noted Assistant Superintendent of Schools Robert
Kuklis.
"Some items have been put off for many years," he added.
The various capital improvements include some new construction, such as the
building of an educational annex at Head O' Meadow School, renovations to
existing but outdated infrastructure in several schools, fire code updates,
roof replacements, repaving of parking lots and funds for the long-anticipated
relocation of the Queen Street administrative offices and remodeling of that
space for conversion into four Middle School classrooms.
Only one more item - upgrading the playing field at the rear of the high
school - was added to a revised version of the five-year list at the board's
December 10 meeting, but it turned out to be an expensive addition, boosting
the total by $500,000.
If approved, that work would be done during year two (1998/99).
"The rear field upgrade was in the original high school project, but then
taken out for budgetary reasons," Dr Kuklis said.
When he introduced the plan December 3, Dr Reed advised board members and the
public at large not to think of the package as "a wish list," but rather as a
"planning document" that pinpoints critical areas where action must be taken
to maintain the town's investment in its public schools.
"If you don't do these things, you're going to be in trouble," Mr Posca said,
echoing Dr Reed's message.
All of the improvements enumerated in the five-year plan are what Mr Posca
considers "must do" action items, such as ceiling and lighting replacements at
Sandy Hook and Middle Gate schools and Department of Environmental Protection
(DEP) mandated work at Head O' Meadow and the Middle School, involving
replacement of the oil tank at Head O' Meadow and handicap and fire code
updates at both schools.
Central Office Relocation
School officials are hoping that a new location will be found for the Board of
Education central office complex that is now located in a small building on
Queen Street adjoining the Middle School.
"Can we get four classrooms out of this?" Dr Reed asked architect Rusty Malek
of Kaestle Boos architectural firm,who was also at the December 3 board
meeting.
The educators and administrators would like to move out of the crowded Queen
Street space, consigning the building for remodeling and use by the Middle
School.
The central office building currently houses not only the superintendent's
office and board meeting room, but the school transportation and pupil
personnel services offices.
The question remains, where will they go?
The possibility of relocating the central office into one of the 48 Fairfield
Hills buildings has been repeatedly posed, but board members noted that they
hadn't been able to get a firm answer from First Selectman Robert Cascella as
to whether or not that would be possible.
As another option, the schools' Space Needs Committee is looking into short
and long-term leasing of commercial space.
Sandy Hook and Middle Gate
Ceiling and lighting replacements costing $65,000 are scheduled for Sandy Hook
School in year three (1999/2000).
At Middle Gate School, ceiling and lighting replacements are slated for year
four (2000/2001) and will cost $58,000. Replacement of the original roof at
Middle Gate (built in 1964) is slated to be done during year three (1999/2000)
at a cost of $385,000.
No Capital Improvements are scheduled for Hawley School because there is
currently a $4 million addition and renovation project currently underway that
has addressed immediate needs and includes code updates throughout the
existing building.
Head O' Meadow
Administrators say a total of $780,000 must be spent at Head O' Meadow
Elementary School over the next five years.
During year one (1997/1998), the oil tank must be replaced in response to a
DEP mandate. That project will cost $50,000.
During year two (1998/1999), code updates must be made throughout the school
in response to fire marshal requirements including ADA compliance and
sprinkler systems at a cost of $400,000. During the same year, the parking lot
is scheduled for repaving at a cost of $80,000.
During year three (1999/2000), an educational annex will be constructed at an
estimated cost of $250,000.
Middle School
The administrators say the Middle School is another facility where a major
amount of money - estimated at $829,000 - must be spent over the next five
years.
The biggest project there would be the conversion during year two (1998/1999)
of the administrative offices to classrooms, estimated to cost $350,000. That
same year, there would be a mandated fire code update costing $200,000 and
refurbishing of auditorium seating and lighting, costing $25,000.
Other improvements to the Middle School would be: year one (1997/1998), the
continuation of vinyl siding on all existing trim, completion of the door
project in the C-Wing and the sewer tie-in; year three (1999/2000), expansion
of the parking area costing $80,000; year four (2000/2001), replacement of
bleachers in the A-Wing gym at a cost of $60,000. No improvements are
scheduled for year five.
Other Projects
With the exception of the $500,000 upgrading of the rear playing field
scheduled for year two (1998/99), there are no improvements planned for the
high school building itself where a $25 million interior renovation and
classroom addition project is now underway.
However, a possible add-on that didn't appear in this year's capital
improvement plan was suggested - replacement of the ventilation units over the
gymnasium.
Architect Rusty Malek said there is $15,000 in the current construction budget
to use toward repair of the ventilation system, but he asked the board whether
the units are, in fact, too old.
"Are they worth repairing?" asked Mr Malek.
In his opinion, the units should be replaced.
Board members wanted to know why Mr Malek hadn't included replacement costs in
the original project estimates.
"We were over budget and had to pare back somewhere," Mr Malek told them.
The board concluded that it might need to go to the Legislative Council for
permission to add this item, under discretionary accounts not originally
budgeted.
A final project that was included in the five-year capital plan, was a $50,000
work and storage facility under the category building and grounds, that is
being proposed during year four (2000/2001).